The Real Story – A Column
When rumors first started swirling that Hillsboro’s power grid was hitting a terminal bottleneck, the Hillsboro Herald dug in and asked questions. Officials pointed to spreadsheets and promised “steady growth.” But the physical evidence on the ground told a completely different story: informants working in a local Data Cebter called to tell us the project was done but would sit dormant. Local landowners told us that major industrial land deals were collapsing in escrow or being extended because Portland General Electric (PGE) told them there wouldn’t be sufficient power available for another three to four years to power the intended users, Data Centers.
The Herald reached out to both the City of Hillsboro and PGE, and no one refuted the premise. We blew that whistle on April 16th of this year. No one else in the press took a swing at this story, and that seemed odd.
Hillsboro May Be Out Of Power: The High Cost of the Data Center “Gold Rush”
Now, the national real estate and tech media are sounding the exact same alarm, validating a reality that has been unfolding right under our noses. A recent national deep-dive by real estate industry outlet GlobeSt confirms that the era of unlimited digital infrastructure growth has officially slammed into a hard wall of utility realities. Across the country, and acutely here in the Pacific Northwest, the immediate availability of massive electrical power—not land, not tax incentives, and not water—is now entirely dictating the future of industrial tech.
From the GLOBE ST. story: https://www.globest.com/2026/06/29/why-power-supply-is-dictating-industrials-new-tech-era/
In Hillsboro, Oregon’s tech corridor, datacenters have consumed so much of the industrial land supply that Portland General Electric has run out of power in the submarket, effectively halting new datacenter development. At the same time, Kidder Mathews EVP Peter Stalick says land prices have climbed beyond the reach of traditional developers.
“The datacenter demand, coupled with the transfer from gas-powered to electric vehicles, continues to overwhelm the existing electrical grid infrastructure,” Stalick says. “The grid in most cities will need to double or triple in size in order to meet the increased electrical demand over the coming 10 to 20 years.” Grabell adds that utilities may take three years or more to upgrade substations.
Read the story here- https://www.globest.com/2026/06/29/why-power-supply-is-dictating-industrials-new-tech-era/
When national brokerages and real estate outlets start explicitly stating that our monopoly utility has “run out of power” and that local land prices are entirely warped, the city can no longer dismiss this as a local worry. It’s a certified market reality.

The Illusion of the 430-Megawatt Promise
The core of the crisis lies in a dangerous game of “paper commitments.” PGE recently acknowledged executing five massive contracts with data center customers totaling a staggering 430 megawatts (MW). To put that in perspective, that is enough electricity to power two entire semiconductor manufacturing campuses the size of Intel’s Ronler Acres.
But while Intel supports roughly 15,000 high-paying local jobs on its power load, these five data centers will create fewer than 300 long-term positions. Worse yet, that power is essentially a phantom lottery ticket.
Utility filings confirm that the primary technical choke point is a transmission bottleneck known as the “North of Pearl” (NOPE) flowgate. In plain terms, the physical transmission wires feeding the North Hillsboro industrial corridor have reached their thermal limit. Pushing more juice through the existing infrastructure would cause lines to overheat, sag, and risk a catastrophic grid failure.
The structural fix, a massive 500kV ultra-high-voltage expansion project to bypass the funnel, is bogged down in permitting and isn’t projected to be operational until May 2030. Until then, the tank is effectively empty.
Enter the “Bring Your Own Power” Movement
Because the utility cannot guarantee continuous juice from traditional transmission lines, a desperate new rule has emerged for tech giants wanting to build in Washington County: Bring Your Own Power (BYOP).
If you want to build a data center, you have to solve your own energy crisis. As documented in our investigation into the BESS battery explosion and Hillsboro’s silent one-gigawatt power shift, the region is rapidly transitioning from a data storage hub into an experimental, decentralized energy grid lined with fields of white metal shipping containers.
Battery Energy Storage Systems (BESS) are no longer just a green energy supplement; they are now the literal life support system for local digital infrastructure. These massive lithium-ion installations act like giant, utility-scale power banks. They pull electricity from the grid during off-peak hours when demand is low, store it, and then discharge it back when the system threatens to collapse under the weight of thousands of humming AI servers.
The sheer scale of this battery gold rush is staggering. Leading the charge is NextEra’s massive 400-megawatt Meadowlark project, planned near the Urban Reserve. But Meadowlark is just the tip of the iceberg. Across North Hillsboro, multiple BESS facilities are quietly sliding through the planning pipeline, collectively aiming to inject nearly a gigawatt of storage capacity directly into the local industrial corridor.
The Pipeline Keeps Growing: CoreSite and Hines Press On
Despite the grid operating at its absolute thermal capacity, the data center gold rush shows no signs of slowing down at City Hall. Massive new projects continue to push through the planning pipelines, seemingly ignoring the infrastructure wall.

Among them are major proposed footprints by global players like CoreSite and a massive campus adjacent to Waibel Creek off of Sewell Road. Also in development is the Hines Data Center project adjacent to the Beaverton Academy of Science and Engineering. These projects are moving forward on paper, joining the ranks of facilities like EdgeConneX’s POR03, which sits structurally finished but effectively “dead on the vine,” waiting for a grid that cannot feed it. Under the BYOP model, developers like these are often forced to integrate massive energy storage or alternative generation directly into their site footprints just to secure local approvals. Coresite has quite a few BESS batteries on its plans. Hines has not shown any as of yet.

The Cost to the Community
This massive power shift isn’t happening in a vacuum, and it isn’t free. While these tech companies and battery developers build out their private mitigation systems, local residential ratepayers are left holding the bag. Until recently, households have absorbed consecutive rate hikes to help fund the broader transmission infrastructure overhauls needed to support this chaotic, high-voltage landscape.
Furthermore, the economic reality is stark. By allowing server farms to lock up the region’s power capacity years before the infrastructure is ready, local leadership has inadvertently sidelined real employers. If a major manufacturing giant wanted to bring thousands of high-paying jobs to Hillsboro tomorrow, the answer from the utility provider could be simple: Wait until 2030, or no deal.
If the grid triggers a brownout this summer, these data centers will simply switch over to their massive battery arrays or spin up rows of semi-truck-sized diesel generators, effectively running a fossil-fuel power plant right in Hillsboro’s backyard, while everyday residents are left in the dark. The battery explosion is proof positive that the tank is empty, and the public is subsidizing the experiment.
And now the Nation is talking about it. Isn’t it time for local officials and other media outlets to do the same?
The Hillsboro Herald: A Note to Our Readers on Corporate Power & Transparency
The Hillsboro Herald is a formally organized LLC under Oregon law. Over the past six years, we have produced nearly 1,000 original news stories. We are a paying member in good standing of the Society of Professional Journalists (SPJ) and the Online News Association (ONA). Syndicated and amplified via Google News and Newsbreak, our reporting is closing in on 10 million reads.
Despite these undisputed facts, the Hillsboro City Attorney and City Manager continue to block the Herald from attending Executive Sessions, hiding behind the claim that we are “not a news source.”
The City’s Official Stance: “The City has considered your request to attend executive sessions as a representative of the news media… [A] representative of the news media is a news gatherer who has a formal affiliation with an institutional news medium… We do not believe that the Hillsboro Herald currently meets this standard.” The City claims a true news medium must possess attributes like a large paid staff and a specific corporate advertising structure.
The facts say otherwise. The Herald has thousands of dedicated subscribers and consistently provides more localized, hard-hitting Hillsboro news than any traditional “institutional” outlet in the region.
We have been offered pro bono legal assistance to sue the City of Hillsboro to force access. We choose not to pursue a lawsuit at this time because city resources are already strained, and we prefer to focus our energy on reporting. However, we are confident the Herald meets every legal standard required to pierce the City’s bureaucratic blockade.
We want you, our readers, to know how deeply committed we are to uncovering the stories no one else will touch. It is for you that we exist.
Furthermore, City Manager Hammond recently took it upon himself to email the Hillsboro and Beaverton School Districts and their respective school boards, claiming that the Herald is merely a “personal website.”

Here is a screenshot from a public email sent by Mr. Hammond to local school boards that was provided to us by one of the Board members. We have raised serious, documented concerns about placing massive industrial data centers directly adjacent to our public schools. This email appears designed to minimize those valid community concerns and undermine our reporting.
The work continues.




















The Hillsboro Herald is a valuable source of information for individuals, who work hard to make a living, and don’t have the time to drop what they are doing to look into the issues that the Herald reports on. I question the reasoning behind the Hillsboro City Manager and City Attorney for not allowing a long-standing source of journalism to not be allowed into executive sessions. What do they know don’t want the public to know??
“The structural fix, a massive 500kV ultra-high-voltage expansion project to bypass the funnel, is bogged down in permitting and isn’t projected to be operational until May 2030.”
It is crazy how long it takes to build a new power line in the USA.